ARCON CYBERCITY is your future-ready home complex with all that you need to live a life full of luxury. The project is conveniently situated opposite to Technopark Phase - 3 and the upcoming Taurus Mall, offering close proximity to Technopark Phase - 1, Infosys Campus, and UST Global as well. Comprising of 2 & 3 BHK premium luxury apartments, these property has been meticulously planned with intelligent space usages, abundance of natural light and is nearing completion in Trivandrum.
 
Refresh yourselves with a rooftop swimming pool featuring state-of-the-art facilities, complete with convenient restrooms and lockers for an enjoyable experience. Families with young ones can bask in the convenience of a dedicated kid's pool, providing a safe and entertaining space for the little ones to splash and play. The rooftop has a carefully designed landscaped party area, offering a picturesque backdrop for social gatherings.
Structure
- RCC framed structure complying with seismic zone 3 designs and as per the structural design. Concrete grade and steel grade be as per structural consultant’s advice.
Doors & Windows
- Entrance door - Teak Veneered Paneled Door with flush shutters.
- Internal doors - Hardwood Frames and flush door shutter.
- Toilet doors - Engineered door frame with water resistant moulded shutters.
- Hardware - All hardware will be in C.P/Brass.
- Lock - Main Door & Bed Room door Locks will be mortise of Godrej/Ozone/Sifon make and Toilet Doors will have “dead” latch of Hettich/Ozone/Sifon
- All regular windows, ventilators and balcony sliding doors will be powder coated aluminum with 5mm glass.
Electrical
- Concealed copper wiring shall be done for lighting, fans, power points, AC points using RR cable/Havells Standard/Havells /Poly cab.
- Wired provision for the water heater point and exhaust fan point shall be provided for all the apartment toilets
- Wired provision for telephone and internet point shall be provided in the living room & master bed room.
- Provision for cable TV/DTH shall be provided in the living room & master bed room.
- Switches: Modular plate switches shall be provided of Legrand (Lincus)/Schneider(Livia)/Havells(Fabio).
- Adequate ELCB and MCB shall be provided in each apartment using Legrand/Schneider/Havells.
- DG Power Back up : Power back up will be provided for all common service and selected light and fan points in living, bed rooms,
TV points and a refrigerator point shall be provided .power back up maximum 600W for each apartment.
(AC point, water heaterpoint and other16Ams point will not be considered for the power back up)
- Light Fixtures: For Common areas, Garden areas and at the top of Main entrance door of individual apartments
sanitary & plumbing
- Master Bed Room Toilet - Wall-hung EWC with concealed flush tanks. Vanity Counter and Wash bowls. All sanitary fittings shall be of CERA, ESSCO by Jaguar.
- Other Bedroom Toilet – Wall hung EWC with concealed flush tanks, wall hung wash basin. All sanitary fittings shall be of CERA/ESSCO by Jaquar.
- Concealed Cistern (Concealed flushing system)– will be of GEBRIT/CERA/JAQUAR.
- CP fittings of all toiles - single lever concealed diverter for shower and spout. Pillar tap shall be provided for washbasin, health faucet with angle valve shall be provided in all bathrooms. All fittings shall be of CERA/ESSCO by Jaquar.
- Hot Water- Provision for hot water shall be provided for all apartment’s overhead shower and spout only.
- Pipes- All supply lines will be with ISI marked CPVC/PVC pipes.
- Kitchen & Work Area- Wall mounted Faucets taps using ESSCO by JAGUAR/CERA brand.
- Kitchen Sink-Stainless Steel sink single bowl with drain board of ISI make for Kitchen, and stainless sink without drain board will be provided for the work area shall be of Prince/Metro.
- Accessories- Accessories like Towel rods, Soap Dish with C.P. finish will be provided inside the toilets. Towel ring shall be provided near dining washbasin
Flooring & Tiling + Railing
- Lift lobby and fascia using compositemarble/granite/vitrified tile as per the architects design.
- Staircase usingvitrified tile and hand railing using MS / G.I sections as per architects design.
- Car park Area Seamless VDF flooring with groove/exterior grade paving tile as per the architects designin specific areas.
- Foyer/Living/Dining/Bed Rooms/Kitchen using 80cm x 80cm vitrified tiles of CERA/KAJARIA/AGL/JOHNSON/QTONE/SOMANY as per architects design.
- Toilets Ceramic tile for floor and for walls up to door height CERA/KAJARIA/AGL/JOHNSON/QTONE/SOMANY as per architects design.
- Balconies Rustic or antiskid ceramic tiles and G.Irailings as per architects design up to 1.20M minimum height.
painting
- Acrylicwall Emulsion paint with putty finish using Asian/Berger/Nerolac in all apartments and in the common areas and utility services areas.
- Regular ceiling emulsion paint Asian/ Berger/Nerolac for the ceiling inside apartments & common areas.
- External Walls Exterior grade emulsion using Asian/Berger/Nerolac.
elevators
- Elevators - 2 Nos. will be provided with automatic doors of OTIS/ JHONSON / THYSSENKRUP/FUJITEC.
air conditioning
- Wired provision for installing split Air-conditioners will be provided for all bed rooms.
automation
- Access control entry at main entrance lobby area.
- Gas leakage cut out valves will be provided in each apartment.
landscaping
- Interlock Pavers to be laid in driveways.
- Entrance Gate as per the architect design.
Water & Electricity
- Bore well water shall be provided for drinking and non drinking purpose through underground sump and overhead tanks.
- 3 phase electricity shall be provided for the apartments.
amenities & features
- Roof top swimming pool with restrooms and lockers.
- Kid’s pool.
- Landscaped roof top party area with BBQ.
- Fully equipped air - conditioned gym with 2Nos Motorized tread mill, 1No. Elliptical cross trainer and 1 home gym
- Multipurpose hall.
- Designer Entrance Lobby.
- Association room.
- Air - conditioned guest suite.
- Kids play area with play equipments.
- Kid’s playroom with indoor games.
- Gazebo with sitting area.
- Badminton court.
- Air - conditioned Mini Movie lounge.
- Ample car parking for visitors.
- Car parking for differently abled.
- Two automatic elevators with rescue device.
- Biometric access at main lobby area.
- CCTV surveillance cameras in key areas.
- Provision for Round the clock security.
- Solar powered lights for lobby areas
- Generator back - up for common areas and designated points in the apartment.
- DTH / cable provision in living and master bedroom.
- Intercom facility between apartments and the security cabin.
- Sewage treatment plant or provision for drainage connection.
- Bio bins for solid waste management.
- Provision for Wi-Fi internet.
- Drivers room with toilets.
- Maid’s toilet.
- Individual letter boxes.
- Shopping trolleys.
- Provision for car wash.
- Owners name board.
- Reticulated gas supply
06-02-2024
Roof Slab Concreting - 100%
Ceiling Plastering
Basement to Terrace Floor | 100% |
Block Work
Basement to Terrace Floor | 100% |
Inside Plastering
Basement to Terrace Floor | 100% |
External Plastering - 100%
Electrical Wall Chasing & Box Fixing
Basement to 16th Floor | 100% |
Electrical Wire Pulling Work
Apartment & Lobby | 100% |
Basement Floor Parking | 100% |
Switch fixing (ADE) | 100% |
Switch fixing (BC) | 50% |
Electrical HT Work
Cable Tray Work | 100% |
Panel Board Work | 100% |
Cable Pulling | 100% |
DG & Transformer | 100% |
Plumbing Works
Core Cutting Work (2nd to 16th Floor | 100% |
Piping Work (2nd to 16th Floor | 100% |
Vertical Shaft Line Work | 100% |
Top Ring Line Work | 100% |
Cp & Sanitary Fixing | 5% |
Waterproofing Works
2nd to 16th Floor | 100% |
Terrace Floor | 100% |
OHT | 100% |
UG Sump Tank | 100% |
2nd Terrace Floor | 100% |
Inside Painting Work (Putty & Primer)
Inside Painting Work (Emulsion)
External Texture Painting
Front Side | 100% |
Right Side of A flat | 100% |
Left Side of D flat | 100% |
B & C Left and Right | 100% |
Rear Side | 100% |
Fire Fighting Work
2nd to 15th Floor | 100% |
16th Floor | 100% |
Inside Vertical Line | 100% |
Fabrication Work
Balcony Handrail (Front side) | 100% |
Balcony Handrail (Right Side) | 100% |
Balcony Handrail (Rear Side) | 100% |
Balcony Handrail (Left Side) | 100% |
Staircase Handrail (17th - Basement) | 100% |
Grill Fixing (A,D,E 2nd-15th) | 100% |
Grill Fixing (B&C) | 100% |
Grill Fixing (B&C) | 100% |
Entrance gate | 50% |
Tiling Work
A,D,E Type: 2nd to 15th Floor | 100% |
B,C Type: 15th to 2nd Floor | 100% |
Staircase & Lobby (2nd-17th Floor) | 100% |
Ground Floor | 100% |
Swimming Pool | 100% |
Toilet False Ceiling Work
A,D,E 2nd to 15th Floor | 100% |
B & C 15th to 10th Floor | 100% |
Lobby | 100% |
Ceiling Fire Pipe Covering Work
Lift Erection - 99%
LPG Riser Work - 100%, Apartment Work - 80%
Aluminium Work (Apartment) - 100%, Staircase window- 100%
Kitchen Slab Granite Work (A,D,E Type) - 100%
Dining Wash Counter Work (A,D,E Type) - 100%
Dining Wash Counter Work (B&C Type) - 100%
Door Fixing Work (A,D,E 2nd-15th floor) - 100%, Door Fixing Work (B&C) - 100%
STP work - 99%
Parking VDF flooring
First Floor | 100% |
Basement Floor | 100% |
Ground Floor | 100% |
UPVC Door and Window Works - 100%
Landscape work - 50%
Yard leveling and interlock - 100%
07-12-2023
Roof Slab Concreting - 100%
Ceiling Plastering
Basement to Terrace Floor | 100% |
Block Work
Basement to Terrace Floor | 100% |
Inside Plastering
Basement to Terrace Floor | 100% |
External Plastering - 100%
Electrical Wall Chasing & Box Fixing
Basement to 16th Floor | 100% |
Electrical Wire Pulling Work
Apartment & Lobby | 100% |
Basement Floor Parking | 100% |
Electrical HT Work
Cable Tray Work | 100% |
Panel Board Work | 100% |
Cable Pulling | 100% |
DG & Transformer | 100% |
Plumbing Works
Core Cutting Work (2nd to 16th Floor | 100% |
Piping Work (2nd to 16th Floor | 100% |
Vertical Shaft Line Work | 100% |
Top Ring Line Work | 100% |
Waterproofing Works
2nd to 16th Floor | 100% |
Terrace Floor | 100% |
OHT | 100% |
UG Sump Tank | 100% |
2nd Terrace Floor | 100% |
Inside Painting Work (Putty & Primer)
External Texture Painting
Front Side | 100% |
Right Side of A flat | 100% |
Left Side of D flat | 100% |
B & C Left and Right | 100% |
Rear Side | 100% |
Fire Fighting Work
2nd to 15th Floor | 100% |
16th Floor | 100% |
Inside Vertical Line | 100% |
Fabrication Work
Balcony Handrail (Front side) | 100% |
Balcony Handrail (Right Side) | 100% |
Balcony Handrail (Rear Side) | 100% |
Balcony Handrail (Left Side) | 100% |
Staircase handrail (17th - Basement) | 100% |
Grill fixing (A,D,E 2nd-15th) | 100% | Grill fixing (B&C) | 90% |
Tiling Work
A,D,E Type: 2nd to 15th Floor | 100% |
B,C Type: 15th to 2nd Floor | 100% |
Staircase & Lobby (2nd-17th Floor) | 100% |
Ground Floor | 100% |
Toilet False Ceiling Work
A,D,E 2nd to 15th Floor | 100% |
B & C 15th to 10th Floor | 100% |
Lobby | 100% |
Ceiling Fire Pipe Covering Work
Lift Erection - 99%
LPG Riser Work - 100%, Apartment Work - 50%
Aluminium Work (A,D,E type) - 80%, Staircase window- 100%
Kitchen Slab Granite Work (A,D,E Type) - 100%
Dining Wash Counter Work (A,D,E Type) - 100%
Dining Wash Counter Work (B&C Type) - 100%
Door Fixing Work (A,D,E 2nd-15th floor) - 100%, Door Fixing Work (B&C) - 10%
STP work - 99%
Parking VDF flooring
First Floor | 100% |
Basement Floor | 100% |
Ground Floor | 100% |
UPVC Door and Window Works - 100%
17-11-2023
Roof Slab Concreting - 100%
Ceiling Plastering
Basement to Terrace Floor | 100% |
Block Work
Basement to Terrace Floor | 100% |
Inside Plastering
Basement to Terrace Floor | 100% |
External Plastering - 100%
Electrical Wall Chasing & Box Fixing
Basement to 16th Floor | 100% |
Electrical Wire Pulling Work
Apartment & Lobby | 100% |
Basement Floor Parking | 100% |
Electrical HT Work
Cable Tray Work | 100% |
Panel Board Work | 100% |
Cable Pulling | 100% |
DG & Transformer | 100% |
Plumbing Works
Core Cutting Work (2nd to 16th Floor | 100% |
Piping Work (2nd to 16th Floor | 100% |
Vertical Shaft Line Work | 100% |
Top Ring Line Work | 100% |
Waterproofing Works
2nd to 16th Floor | 100% |
Terrace Floor | 100% |
OHT | 100% |
UG Sump Tank | 100% |
2nd Terrace Floor | 100% |
Inside Painting Work (Putty & Primer)
External Texture Painting
Front Side | 100% |
Right Side of A flat | 100% |
Left Side of D flat | 100% |
B & C Left and Right | 100% |
Rear Side | 100% |
Fire Fighting Work
2nd to 15th Floor | 100% |
16th Floor | 100% |
Inside Vertical Line | 100% |
Fabrication Work
Balcony Handrail (Front side) | 100% |
Balcony Handrail (Right Side) | 100% |
Balcony Handrail (Rear Side) | 100% |
Balcony Handrail (Left Side) | 100% |
Staircase handrail (17th - Basement) | 100% |
Grill fixing (A,D,E 2nd-15th) | 100% | Grill fixing (B&C) | 40% |
Tiling Work
A,D,E Type: 2nd to 15th Floor | 100% |
B,C Type: 15th to 2nd Floor | 100% |
Staircase & Lobby (2nd-17th Floor) | 100% |
Toilet False Ceiling Work
A,D,E 2nd to 15th Floor | 100% |
B & C 15th to 10th Floor | 100% |
Lobby | 50% |
Ceiling Fire Pipe Covering Work
Lift Erection - 97%
LPG Riser Work - 100%, Apartment Work - 10%
Aluminium Work (A,D,E type) - 80%, Staircase window- 50%
Kitchen slab granite work (ADE Type) - 100%
Dining wash counter work (ADE Type) - 100%
Dining wash counter work (B&C Type) - 100%
Door fixing work (ADE 2nd-6th floor) - 100%
STP work - 98%
Parking VDF flooring
Dining wash counter work (B&C Type) - 100%
First Floor | 100% |
Basement Floor | 100% |
19-10-2023
Roof Slab Concreting - 100%
Ceiling Plastering
Basement to Terrace Floor | 100% |
Block Work
Basement to Terrace Floor | 100% |
Inside Plastering
Basement to Terrace Floor | 100% |
External Plastering - 100%
Electrical Wall Chasing & Box Fixing
Basement to 16th Floor | 100% |
Electrical Wire Pulling Work
Apartment & Lobby | 100% |
Basement Floor Parking | 80% |
Electrical HT Work
Cable Tray Work | 100% |
Panel Board Work | 100% |
Cable Pulling | 100% |
DG & Transformer | 100% |
Plumbing Works
Core Cutting Work (2nd to 16th Floor | 100% |
Piping Work (2nd to 16th Floor | 100% |
Vertical Shaft Line Work | 100% |
Top Ring Line Work | 100% |
Waterproofing Works
2nd to 16th Floor | 100% |
Terrace Floor | 100% |
OHT | 100% |
UG Sump Tank | 100% |
2nd Terrace Floor | 100% |
Inside Painting Work (Putty & Primer)
External Texture Painting
Front Side | 100% |
Right Side of A flat | 100% |
Left Side of D flat | 100% |
B & C Left and Right | 100% |
Rear Side | 100% |
Fire Fighting Work
2nd to 15th Floor | 100% |
16th Floor | 10% |
Inside Vertical Line | 60% |
Fabrication Work
Balcony Handrail (Front side) | 100% |
Balcony Handrail (Right Side) | 100% |
Balcony Handrail (Rear Side) | 100% |
Balcony Handrail (Left Side) | 100% |
Staircase handrail (17th - Basement) | 100% |
Grill fixing (A,D,E 2nd-12th) | 100% |
Tiling Work
A,D,E Type: 2nd to 15th Floor | 100% |
B,C Type: 15th to 2nd Floor | 100% |
Staircase & Lobby (2nd-17th Floor) | 100% |
Toilet False Ceiling Work
A,D,E 2nd to 15th Floor | 100% |
B & C 15th to 10th Floor | 100% |
Ceiling Fire Pipe Covering Work
Lift Erection - 95%
LPG Riser Work - 100%, Apartment Work - 10%
Aluminium Work (A,D,E type) - 80%
Kitchen slab granite work (ADE Type) - 100%
Dining wash counter work (ADE Type) - 100%
Dining wash counter work (B&C Type) - 100%
Door fixing work (ADE 2nd-6th floor) - 100%
STP work - 80%
Parking VDF flooring
Dining wash counter work (B&C Type) - 100%
10-08-2023
Roof Slab Concreting - 100%
Ceiling Plastering
Basement to Terrace Floor | 100% |
Block Work
Basement to Terrace Floor | 100% |
Inside Plastering
Basement to Terrace Floor | 100% |
External Plastering - 100%
Electrical Wall Chasing & Box Fixing
Basement to 16th Floor | 100% |
Electrical Wire Pulling Work
2nd to 15th Floor | 100% (A,D,E) |
15th to 2nd Floor (B & C) | 100% |
Lobby-15th-12 | 100% |
Electrical HT Work
Cable Tray Work | 100% |
Panel Board Work | 100% |
Cable Pulling | 100% |
DG & Transformer | 50% |
Plumbing Works
Core Cutting Work (2nd to 16th Floor | 100% |
Piping Work (2nd to 16th Floor | 100% |
Vertical Shaft Line Work | 100% |
Top Ring Line Work | 95% |
Waterproofing Works
2nd to 16th Floor | 100% |
Terrace Floor | 100% |
OHT | 100% |
UG Sump Tank | 100% |
2nd Terrace Floor | 100% |
Inside Painting Work (Putty & Primer)
External Texture Painting
Front Side | 100% |
Right Side of A flat | 100% |
Left Side of D flat | 100% |
B & C Left and Right | 100% |
Rear Side | 100% |
Fire Fighting Work
2nd to 15th Floor | 100% |
16th Floor | 10% |
Inside Vertical Line | 60% |
Fabrication Work
Balcony Handrail (Front side) | 100% |
Balcony Handrail (Right Side) | 100% |
Balcony Handrail (Rear Side) | 100% |
Balcony Handrail (Left Side) | 100% |
Staircase handrail (17th - Basement) | 100% |
Tiling Work
A,D,E Type: 2nd to 15th Floor | 100% |
B,C Type: 15th to 3rd Floor | 90% |
Toilet False Ceiling Work
A,D,E 2nd to 15th Floor | 100% |
B & C | 10% |
Ceiling Fire Pipe Covering Work
Lift Erection - 75%
LPG Riser Work - 80%
Aluminium Work (ADE type) - 30%
Note: - Aluminium works, Grill works were completed in Sample apartment
06-07-2023
Roof Slab Concreting - 100%
Ceiling Plastering
Basement to Terrace Floor | 100% |
Block Work
Basement to Terrace Floor | 100% |
Inside Plastering
Basement to Terrace Floor | 100% |
External Plastering - 100%
Electrical Wall Chasing & Box Fixing
Basement to 16th Floor | 100% |
Electrical Wire Pulling Work
2nd to 15th Floor | 100% (A,D,E) |
15th to 7th Floor (B & C) | 100% |
06th Floor (B & C) | 50% |
Electrical HT Work
Cable Tray Work | 100% |
Panel Board Work | 100% |
Cable Pulling | 100% |
Plumbing Works
Core Cutting Work (2nd to 16th Floor | 100% |
Piping Work (2nd to 16th Floor | 100% |
Vertical Shaft Line Work | 80% |
Top Ring Line Work | 25% |
Waterproofing Works
2nd to 16th Floor | 100% |
Terrace Floor | 100% |
OHT | 100% |
UG Sump Tank | 40% |
2nd Terrace Floor | 80% |
Inside Painting Work (Putty & Primer)
External Texture Painting
Front Side | 100% |
Right Side of A flat | 100% |
Right Side of D flat | 100% |
Rear Side | 30% |
Fire Fighting Work
2nd to 15th Floor | 100% |
16th Floor | 10% |
Fabrication Work
Balcony Handrail (Front side) | 100% |
Balcony Handrail (Right Side) | 100% |
Balcony Handrail (Rear Side) | 100% |
Balcony Handrail (Left Side) | 100% |
Staircase handrail (17th - 7th Floor) | 100% |
Tiling Work
A,D,E Type: 2nd to 15th Floor | 100% |
B,C Type: 15th to 8th Floor | 90% |
Toilet False Ceiling Work
Ceiling Fire Pipe Covering Work
Lift Erection - 50%
Note: - Aluminium works, Grill works were completed in Sample apartment
13-06-2023
Roof Slab Concreting - 100%
Ceiling Plastering
Basement to Terrace Floor | 100% |
Block Work
Basement to Terrace Floor | 100% |
Inside Plastering
Basement to Terrace Floor | 100% |
External Plastering - 100%
Electrical Wall Chasing & Box Fixing
Electrical Wire Pulling Work
2nd to 15th Floor | 100% (A,D,E) |
15th Floor (B & C) | 100% |
14th Floor (B & C) | 100% |
13th Floor (B & C) | 100% |
12th Floor (B & C) | 50% |
Electrical HT Work
Cable Tray Work | 100% |
Panel Board Work | 100% |
Cable Pulling | 100% |
Plumbing Works